The Michigan Supreme Court will review a challenge by Tribal Nations and environmental advocates against the MPSC’s approval of Enbridge’s proposed oil tunnel under the Straits of Mackinac. The case centers on claims that the approval ignored state laws and failed to evaluate environmental risks associated with the tunnel project. Critics argue it threatens local ecosystems and Indigenous rights, while Enbridge defends its permitting process as thorough, claiming it will enhance safety. This pivotal review could shape future discussions on energy infrastructure and environmental protection in Michigan.

Michigan – The Michigan Supreme Court will review a significant legal challenge brought forth by Tribal Nations and environmental advocates against the Michigan Public Service Commission’s (MPSC) approval of Enbridge’s proposed oil tunnel beneath the Straits of Mackinac. This case centers around claims that the MPSC ignored state laws in its 2023 decision, which allows Enbridge to construct a large concrete tunnel meant to house a new section of the Line 5 pipeline.

Enbridge’s current operations involve dual pipelines that transport oil and gas through open water, a method deemed controversial due to environmental risks. According to Earthjustice, a nonprofit organization representing the challenge, these pipelines transport up to 23 million gallons of oil and gas daily, which contravenes a 2020 shutdown order mandated by the State of Michigan.

Critics, including Whitney Gravelle, president of the Bay Mills Indian Community, argue that the proposed tunnel threatens the integrity of local ecosystems, particularly the clean water and fishing resources in the area. The legal petition for the challenge has been filed by the Bay Mills Indian Community and other Tribal nations, including the Little Traverse Bay Bands of Odawa Indians and the Grand Traverse Band of Ottawa and Chippewa Indians, all expressing deep concerns regarding the potential environmental impacts of tunneling.

Support for the Challenge

The tribes, alongside backing from groups such as the Michigan Climate Action Network and the Environmental Law & Policy Center, assert that the MPSC failed to properly evaluate the environmental risks associated with the tunnel project, especially regarding the possibility of oil spills. The challenge emphasizes the necessity for a comprehensive review by the MPSC to ensure the safety and well-being of Michigan residents.

Representatives from the environmental advocacy community have highlighted that the potential impacts on treaty-protected rights of Tribal Nations were not sufficiently addressed during the approval process. This aspect has drawn further criticism towards the MPSC’s assessment procedures.

Enbridge’s Position

Enbridge remains confident in the MPSC’s permitting process, asserting that it was thorough and justified. The company argues that relocating Line 5 into the proposed tunnel will improve safety measures significantly and protect crucial natural resources in the region while ensuring continued energy access for the Midwest.

In an earlier ruling, the Michigan Court of Appeals upheld the MPSC’s decision allowing the project, which now sets the stage for a pivotal review by the state’s highest court. The implications of this review could significantly shape future discussions regarding the safety and viability of Line 5.

Broader Context

This legal battle unfolds against the backdrop of ongoing debates regarding energy infrastructure, environmental stewardship, and Indigenous rights in Michigan. While some advocacy groups and Tribal leaders call for the decommissioning of Line 5 altogether, others highlight the project as a vital component of the Midwest’s energy reliability, with approximately 70% of Michiganders reportedly expressing support for the infrastructure project.

In addition to the state-level legal proceedings, the U.S. Supreme Court is also contemplating whether the 2020 shutdown order issued by Michigan should fall under state or federal jurisdiction, which could further influence the future of Line 5 and the proposed tunnel project.

The Michigan Supreme Court’s decision will be closely monitored, as it will reflect the balance between fulfilling energy needs and protecting environmental and Indigenous rights, a dynamic that continues to evoke strong opinions from various stakeholders within the state.

Deeper Dive: News & Info About This Topic

STAFF HERE GRANDRAPIDS WRITER
Author: STAFF HERE GRANDRAPIDS WRITER

GRAND RAPIDS STAFF WRITER The GRAND RAPIDS STAFF WRITER represents the experienced team at HEREGrandRapids.com, your go-to source for actionable local news and information in Grand Rapids, Kent County, and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as ArtPrize, Festival of the Arts, and World of Winter. Our coverage extends to key organizations like the Grand Rapids Chamber of Commerce and Grand Rapids Community Foundation, plus leading businesses in furniture, healthcare, and technology that power the local economy such as Steelcase, Spectrum Health, and Meijer. As part of the broader HERE network, including HEREDetroitMI.com, HERENorthville.com, HERENovi.com, and HEREPlymouth.com, we provide comprehensive, credible insights into Michigan's dynamic landscape.